The Situation
This large county school system had one of their largest high schools that needed major HVAC upgrades to a 35-year-old system. The project presented multiple logistical challenges including the need to remove and replace a significant amount of steel and copper piping located above ceilings, re-insulate the pipe, and have it operational in just 7 weeks during the summer break.
Our Approach
We developed a phased execution plan that maximized the limited summer window while ensuring all systems would be fully operational before students returned. Our team coordinated closely with the school district's facilities management to minimize disruption to other summer activities.
The Work
- Removal and replacement of 2.5 miles of chilled water and hot water heating piping
- Installation of 117 four-pipe fan coil units serving the school
- Integration of new units into the existing building automation system
- Complete re-insulation of all new piping systems
- Comprehensive testing and commissioning of all equipment
Special Coordination Requirements
The project required careful coordination with the school's summer programs and maintenance activities. All major equipment installation was scheduled during specific windows to avoid conflicts with ongoing educational activities and facility maintenance.