Boiler Room Retrofit - State Office Complex

Conversion from high-temp to efficient low-temp variable flow system with zero interruption to government operations

CLIENT
State Government Agency

LOCATION
Government Office Complex

PROJECT TYPE
Boiler System Retrofit and Modernization

FACILITY TYPE
Large Government Office Complex

The Situation

This large government facility had a centralized hot-temp water system which was scheduled for decommissioning. The old system included an aging two pipe changeover heating and chilled water piping system, which included high-temp hot water heat exchangers from their previous integration project. This is a very busy government complex which could not afford to interrupt their daily operations.

Our Approach

We designed a comprehensive retrofit that converted the existing high-temperature system to a modern, efficient low-temperature variable flow system. The new design provided improved efficiency while maintaining the ability to serve the existing building infrastructure.

The Work

Special Coordination Requirements

Several factors complicated this project. First, the boiler flue needed to be installed within an existing masonry chimney which extended from the basement to the roof of a stories above. The boiler plant was located in the existing mechanical equipment room in the parking garage. Our team designed a plan which would complete all work while enabling this facility to remain operational during the upgrade.

Key Challenges

Our Solution

The Results

This project was a huge success, since we completed the full project on-time and within budget and this resulted in high customer satisfaction. Our customer appreciated the substantial energy savings, improved comfort and efficiency of their new condensing boilers. Our customer was also pleased that they saved for our help with another project to achieve similar additional energy and cost savings.